Land use plan - update (status: "draft")
To get you in the mood for the topic, please first take the time to read the "FAQ - frequently asked questions and answers (PDF)" on the land use plan (FNP).
Please get an overview of the most important legally prescribed procedural steps and the "Stages of the update (PDF)".
Current procedural status: FNP "draft"
The land use plan "preliminary draft" has been transferred to the "draft " planning status. The "draft" planning status of the updated land use plan, which was approved by the City Council by resolution 25/0366-BV on 25.06.2025 and designated for publication, consists of the following components:
- FNP draft - plan section
- FNP draft - explanatory memorandum
- Draft FNP - supplementary map "Adaptation to climate change"
- Draft FNP - Environmental report with appendix
These can be viewed under "Downloads".
Auszug aus der Videobotschaft des Oberbürgermeisters vom 15.08.2025
Why is an FNP update necessary?
Obligation to draw up and update the land use plan
In accordance with Section 5 in conjunction with Section 1 (3) of the German Building Code (BauGB), the preparation and updating of the land use plan is a mandatory municipal task. The land use plan (FNP-2006), which has been effective since 2006, is updated as the framework conditions for urban development and the planning objectives are constantly evolving. The aim and purpose of the planning is to ensure long-term and sustainable municipal development against the background of demographic change, the provision of housing in Jena, securing the city as a business location and the consequences of climatic changes.
Changes to the 2006 FNP
When the FNP-2006 was drawn up, the 2003 household and population forecast still assumed a declining population trend. Since then, Jena has continued to develop. The 2014 household and population forecast and the current 2019 forecast predict positive development trends for Jena. Due to the dynamic development in the regional center of Jena, the designation of new building areas will also have to be taken into account in the FNP update. Due to the limited amount of land available in Jena, a strategically sensible approach to land use is required. Priorities must be set here for sustainable economic and social development, taking ecological effects into account.
What is the basis for the update?
Consolidation of the sectoral development plans
The basis for the FNP update is the city's various sectoral development plans. These have been updated in recent years on the basis of the current population and budget forecasts and supported by the majority of city council resolutions.
In addition, the "Integrated Urban Development Concept Jena.2030+" (ISEK), which was drawn up in a broad-based coordination process and adopted by the city council, provides cross-departmental guidelines for future urban development. Corresponding recommendations for adapting the land use plan were compiled in the ISEK and serve as a basis for updating it.
A selection of important principles and specialist plans can be found here:
- Population forecast 2035
- Integrated urban development concept ISEK Jena 2030
- Residential development area concept 2035
- Workplace and commercial space concept 2035
- Public transport concept Jena 2030+
- Landscape plan
- Retail development
- Development concept for the rural villages
- Garden development concept
- Urban climate concept
How does the participation procedure for the FNP update work?
Opportunities for public participation in accordance with the German Building Code (BauGB)
The public is involved in the update process as part of the formal procedural steps in accordance with the German Building Code (BauGB). In accordance with the nationally prescribed procedure, the public and the authorities involved have the opportunity to comment in (at least) two different procedural steps as part of the preparation process:
- Stage 1: Early participation in the "preliminary draft" planning status [Section 3 (1) BauGB] or [Section 4 (1) BauGB]
- Stage 2: Public display of the "draft" [Section 3 (2) BauGB] or [Section 4 (2) BauGB]
Stage 1
Citizens are informed about the planning intentions in the early public participation phase. The objectives and purposes of the planning with regard to the spatial development of the city are presented in the "preliminary draft". The preliminary draft is made available to the public for this purpose. The method of early information will be announced in the official gazette. Further information is also available on the Internet. Citizens have the opportunity to submit comments on the preliminary draft during the public display period. The authorities and public agencies involved will be given the opportunity to comment.
All comments received are examined to determine in what form and to what extent they can be incorporated into the further development of the plan. The result of this review process is the "draft" (stage 2). The law does not provide for information on the result of the review or the type of consideration to be given during early public participation (stage 1). We therefore recommend that you follow the further planning procedure*. In particular, please examine the "draft" plan (stage 2) presented in accordance with Section 3 (2) BauGB as part of the public participation process. This will give you another opportunity to comment if you wish.
Stage 2
In the second stage of public and official participation, the "draft" of the land use plan is put on public display. The location and duration of this public display are published in the official gazette at least one week in advance. Further information is also available on the Internet. Anyone can make suggestions regarding the draft during the public display period. The authorities and public agencies involved will be given the opportunity to comment. All comments on the "draft" (stage 2) are in turn examined in an extensive and complex process to determine in what form and to what extent they can be incorporated into the further development of the plan.
The result of the examination is presented to the City Council for a decision; the City Council weighs up the public and private interests against each other and among themselves and also decides on how to deal with the comments you have made. This is done with the decision on the weighing of interests*.
The result of the consideration is communicated in accordance with Section 3 (2) sentence 4 BauGB. Depending on the scope and complexity of the planning procedure, this may take some time. The final version of the planning is prepared taking into account the result of the consideration and submitted to the city council for approval.
* Notes:
The dates of public displays are published in the official gazette of the City of Jena. The agendas of the city council are also regularly published in the official gazette. The official gazette can be accessed on the municipal website. The city council's calendar of meetings, including all agendas, can be found here.
Information on the handling of your data can be found in this document: Information obligation according to Art. 13 General Data Protection Regulation (GDPR) (PDF).
Previous procedural steps of the update - "preliminary draft" of the FNP
Stage 1: "Preliminary draft" of the land use plan (11/2022)
After the update of the land use plan was approved by the city council on 15/11/2017 with the decision to initiate it(see Official Gazette 50/17 [PDF]), the "preliminary draft" planning status was open to the public at an early stage from 20/02/2023 up to and including 31/03/2023.
The public was given the opportunity to comment during this period (participation phase 1).
The planning status "preliminary draft", consisting of the plan components plan section / explanatory statement / environmental report, can be viewed here.
The handling of the comments received on the FNP "preliminary draft" was approved by the Jena City Council on 25.06.2025. The corresponding table is available as Annex 1a to resolution 25/0366-BV "Approval and interpretation resolution on the draft plan status" here under item Ö 22.
Previous procedural steps of the update - "Draft" of the FNP
Stage 2: " Draft" of the land use plan (03/2025)
After the draft land use plan was approved by the city council with resolution 25/0366-BV "Approval and publication decision on the draft" on 25.06.2025(see Official Gazette 27/25 [PDF]), the "draft" was open for participation from 22.08.2025 to 22.10.2025 inclusive.
The "draft" was thus made available to a broad section of the population over a period of two months and they were given the opportunity to comment (participation phase 2), significantly extending the one-month period stipulated in the German Building Code.
The "draft" with the plan section (main map) and the supplementary explanatory memorandum with climate and environmental report can be viewed under "Downloads".
How can I get involved?
There iscurrently no participation.
The participation period for the "draft" of the land use plan (participation phase 2) ended on 22.10.2025. The participation platform is closed and participation in the FNP "draft" is no longer possible.
The review of all comments received on the FNP "draft" is followed by the decision to weigh them up. The final approval version of the FNP can be submitted to the higher administrative authority with the subsequent decision to approve.