B-Lb 03 Camburger Straße Part I (Löbstedt)
Procedure
- Decision to initiate: 15.01.1992
- Resolution on statutes: 20.11.1996
- Legal force through public announcement: 06.03.1997
Plan content
The majority of the planned area was used by the CIS armed forces until 1992. After release by the armed forces, the land was taken over by the state of Thuringia. The aim of the development plan is to put the area to a new use, taking into account its location in the urban area, and to ensure its orderly urban development.
Of the total area of the area of application, which comprises approx. 28 ha, approx. 15.5 ha are designated as general residential area (WA), approx. 8.5 ha as mixed area (MI) and approx. 4 ha as public traffic area. The number of full storeys is limited to 4 to 6, depending on the building area, and a maximum building height of 16 m is specified for some areas.
Realisation status
The site is fully developed and almost completely built up [July 2018].
Important note
The documents attached as downloads are for information purposes only. Only the legally binding copy of the plan, which can be viewed at the Urban Planning Department, is authoritative.